Ceiling Project Updates

*This is an indicative render and is subject to final design

Exciting things to come

We have commenced our Ceiling Project to introduce our new contemporary ceiling and enhance your shopping experience.  The project will take approximately 10 months to complete and will result in our ceilings receiving a beautiful facelift. The project will have a staggered approach, but no stores will be affected and all stores will be open and trading.  

Work in Progress

The works are being done in the following areas

The skylights in the following area have been completed:
Cybertronics  3 - 9 February
Falco Milano  8 - 10 March
Fragrance Boutique   18 - 19 March 
Anysberg Biltong  8 - 9 April 
Pop Skin  10 -11 May 
IQOS  18 May 

The court spaces in the following areas are being worked on:
Pick n Pay court   Completed 
H&M court  4 March - 30 July
Dischem court  12 April - 13 August
Woolworths Court   26 April - 30 July
Game Court   17 May - 31 August 
Edgars Court  30 June - 25 October 
Food Court  30 June - 24 September 

The walkways in the following areas are being worked on:

Start February
Entrance 1: KFC to Ambeans  Completed 
American Swiss to Poetry  10 February - 30 July 
Entrance 3: Mugg & Bean to Limnos
 Completed 
Entrance 4: Cellucity to Annique  12 February -  30 July

Start March
iStore - @Home
 1 March - 23 July 
Foschini - Time Watch Specialists   11 March - 23 July 
Anysberg - MTN   Completed
FNB - Pandora   17 March - 23 July 
Mat & May - LTD  15 March - 23 July
Vodashop - Verimark
 Completed 
Curiosity Hut - Under Armour   25 March - 23 July 
BT Games - Torga Optical   25 March - 23 July
MRP - Crossley & Sons   25 March - 30 July
Seattle - Crocs   25 March - 30 July

Start April 
Exclusive Books - Spur  15 April - 17 September 


Start May
Cell C - Sheet Street   14 May - 30 July  
Game - Nedbank   31 May - 17 September 


FAQs


Q: Are any Entrances closed?
A: All entrances are currently open.

Q: Will this project affect the trading of stores?
A: All stores will trade for the duration of the ceiling project. Construction work will be carried out after trading hours.

Q: When will the ceiling project be completed?
A: This is a 10-month project, and our aim is for it to be completed by October 2021.

Q: Will construction be taking place throughout the mall or only in some sections?
A: Construction will take place at 3 different places in the mall at a time over a 3-week period, before it moves on to another section until completion of the entire mall's ceiling.

For all queries and compliments, email management@somersetmall.co.za